Construction and Erection of a Flocculant Plant

Type of Contract / Completion:Flockungsmittelanlage

EPCM, 2013-2014

Scope of Supply and Services:

Construction and erection of a flocculant plant with 11 reactors, 22 storage tanks and 26 process tanks: engineering, procurement, implemantation / installation and commissioning of the complete EIC and process control engineering.

  • sensor system and actuating elements
  • process control system
  • distribution of power and light
  • emergency lighting
  • ELA-plant
  • fire alarm systems
  • CCTV systems
  • lightning protection

Technical Key Figures Engineering:Flockungsmittelanlage

Order volume: about 22.000 hours
ICS: about 1.500
Electrical motors: 120
Clusters: 39
Remote I/O Stations: 16
Control system: PCS7 V8.0

Technical Key Figures Installation and Erection:

Order volume: about 8.700 hours
Lightning: about 521 lamps
Main and site streets: about 7.800 m
Cable installation: about 75.000 m

About Griesemann Group

The businesses belonging to the group of companies, INDUREST, JBV, JBV-INDUREST, GMR and Blitzschutz Graff, combine almost all specialist trades for industrial plant engineering and construction, and through a synergetic cooperation of all business units are capable of realising not only complete turnkey projects but also operations-driven individual projects.